Difference between cofferdams and caissons
Cofferdams and caissons are both structures that are used when undertaking construction works in areas submerged in under water.
The main difference between the two is that a cofferdam is a temporary structure which is removed after completion of the work, whereas a caisson is built to remain in place as part of the completed structure.
The aim of a cofferdam is to be as watertight as possible to create a dry area in which to carry out the required works, or at least to limit water ingress to a safe level that can be pumped away.
A caisson is typically a box-like structure made of materials such as timber, steel, masonry and reinforced concrete. It may be constructed onshore then floated to the required location, where it is sunk into place, enabling access to the bed to undertake works.
The type of structure being built will determine whether a caisson or a cofferdam is most suitable. The two principal factors influencing the choice are the ground conditions and the depth to which the work is to be taken. In general, cofferdams are suitable for depths of up to 18 m below high water level, while caissons are more suitable for greater depths.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Licensing construction; looking back to look forward
Voluntary to required contractors (licensing) schemes.
A contractor discusses the Building Safety Act
A brief to the point look at changes that have occurred.
CIOB Construction Manager of the Year award
Shortlist set to go head-to-head for prestigious industry title.
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.